Phase 2 Overview
Phase 2 of LGL’s tool development will expand the existing BOM extraction solution by:
- Matching with Jose Master Part List to automate part number matching and leverage UpKeep work order template for upload to UpKeep
- Changes to the UX and Front-end design of the app to support new user interactions, including homepage edits, uploading Parts List file (this can be re-uploaded) and Missing Part Notification.
- Adding support for MTO files into workflow ****
Duration: 5-7 weeks
Total Build Budget: $38,200
- Phase 2A (LGL Part Number & UpKeep Integration): $20,800
- Phase 2B (Home screen & MTO): $17,400
User Stories: Phase 2 Completion
1️⃣ Access BOM Extractor Dashboard →
2️⃣ User selects processing option →
3️⃣ **Upload content (ISO / MTO)**→
4️⃣ Part number matching to Jose Master Lookup →
5️⃣ Create Work Order Template for UpKeep Upload →
6️⃣ User Clicks Download BOM or Download UpKeep File
Step 1: Access BOM Extractor
- User logs into the BOM ****Extractor.
- Dashboard presents two primary processing paths:
- Isometric Drawing Upload (Hatch or IKO)
- MTO File Upload (Pre-extracted BOM data)
Step 2: Select Processing Options
User is prompted to select from three dropdown menus:
- Format: Hatch or IKO (for isometric drawings)